A simulation and evaluation of earned value metrics to forecast the project duration
Mario Vanhoucke and
S Vandevoorde
Additional contact information
S Vandevoorde: Fabricom Airport Systems
Journal of the Operational Research Society, 2007, vol. 58, issue 10, 1361-1374
Abstract:
Abstract In this paper, we extensively review and evaluate earned value (EV)-based methods to forecast the total project duration. EV systems have been set up to deal with the complex task of controlling and adjusting the baseline project schedule during execution, taking into account project scope, timed delivery and total project budget. Although EV systems have been proven to provide reliable estimates for the follow-up of cost performance within our project assumptions, they often fail to predict the total duration of the project. We present an extensive simulation study where we carefully control the level of uncertainty in the project, the influence of the project network structure on the accuracy of the forecasts and the time horizon where the EV-based measures provide accurate and reliable results. We assume a project setting where project activities and precedence relations are known in advance and do not consider fundamentally unforeseeable events and/or unknown interactions among various actions that might cause entirely unexpected effects in different project parts. This is the first study that investigates the potential of a recently developed method, the earned schedule method, which improves the connection between EV metrics and the project duration forecasts.
Keywords: project management; simulation; forecasting (search for similar items in EconPapers)
Date: 2007
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (11)
Downloads: (external link)
http://link.springer.com/10.1057/palgrave.jors.2602296 Abstract (text/html)
Access to full text is restricted to subscribers.
Related works:
Working Paper: A simulation and evaluation of earned value metrics to forecast the project duration (2005) 
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:pal:jorsoc:v:58:y:2007:i:10:d:10.1057_palgrave.jors.2602296
Ordering information: This journal article can be ordered from
http://www.springer. ... search/journal/41274
DOI: 10.1057/palgrave.jors.2602296
Access Statistics for this article
Journal of the Operational Research Society is currently edited by Tom Archibald and Jonathan Crook
More articles in Journal of the Operational Research Society from Palgrave Macmillan, The OR Society
Bibliographic data for series maintained by Sonal Shukla () and Springer Nature Abstracting and Indexing ().