On the project risk baseline: integrating aleatory uncertainty into project scheduling
Fernando Acebes,
David Poza,
Jose M Gonzalez-Varona,
Javier Pajares and
Adolfo Lopez-Paredes
Papers from arXiv.org
Abstract:
Obtaining a viable schedule baseline that meets all project constraints is one of the main issues for project managers. The literature on this topic focuses mainly on methods to obtain schedules that meet resource restrictions and, more recently, financial limitations. The methods provide different viable schedules for the same project, and the solutions with the shortest duration are considered the best-known schedule for that project. However, no tools currently select which schedule best performs in project risk terms. To bridge this gap, this paper aims to propose a method for selecting the project schedule with the highest probability of meeting the deadline of several alternative schedules with the same duration. To do so, we propose integrating aleatory uncertainty into project scheduling by quantifying the risk of several execution alternatives for the same project. The proposed method, tested with a well-known repository for schedule benchmarking, can be applied to any project type to help managers to select the project schedules from several alternatives with the same duration, but the lowest risk.
Date: 2024-05
New Economics Papers: this item is included in nep-ppm
References: View references in EconPapers View complete reference list from CitEc
Citations:
Published in Computers & Industrial Engineering, 160(2021), 107537. 2021
Downloads: (external link)
http://arxiv.org/pdf/2406.00077 Latest version (application/pdf)
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:arx:papers:2406.00077
Access Statistics for this paper
More papers in Papers from arXiv.org
Bibliographic data for series maintained by arXiv administrators ().