Siting and Curtailment Depth Limit the Grid Headroom Available to New Large Loads
Nils Johnson,
Geoff Blanford and
John E. T. Bistline
Papers from arXiv.org
Abstract:
Data center demand is increasing faster than generation can be built, encouraging proposals to interconnect large loads on condition that they reduce consumption during high-stress periods. Estimates of how much load can be added via flexibility rest on simplified accounting and report only annual curtailed electricity. Here we use a national energy systems model that co-optimizes hourly generation and load curtailment across 16 U.S. regions to characterize the flexibility and power system impacts of enabling headroom. While 50 GW can be served while curtailing less than 0.1% of its annual energy, small annual curtailment conceals potentially severe operating requirements. Most regions require curtailment deeper than 90% in at least one hour, so the load must disconnect or have sufficient on-site resources to provide full back up. Furthermore, announced data center locations are not aligned with modeled headroom and relying on existing generation fleets raises CO2 emissions and wholesale electricity prices.
Date: 2026-10
References: Add references at CitEc
Citations:
Downloads: (external link)
https://arxiv.org/pdf/2611.00462 Latest version (application/pdf)
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:arx:papers:2611.00462
Access Statistics for this paper
More papers in Papers from arXiv.org
Bibliographic data for series maintained by arXiv administrators ().