On Commercial Construction Activity's Long and Variable Lags
David Glancy,
Robert Kurtzman and
Lara Loewenstein
No 24-14, Working Papers from Federal Reserve Bank of Cleveland
Abstract:
We use microdata on the phases of commercial construction projects to document three facts regarding time-to-plan lags: (1) plan times are long—about 1.5 years—and highly variable, (2) roughly 40 percent of projects are abandoned in planning, and (3) property price appreciation reduces the likelihood of abandonment. We construct a model with endogenous planning starts and abandonment that matches these facts. The model has the testable implication that supply is more elastic when there are more "shovel ready" projects available to advance to construction. We use local projections to validate that this prediction holds in the cross-section for US cities.
Keywords: commercial real estate; construction; time-to-plan (search for similar items in EconPapers)
JEL-codes: E22 E32 L74 R33 (search for similar items in EconPapers)
Pages: 44
Date: 2024-06-27
New Economics Papers: this item is included in nep-ppm and nep-ure
References: View references in EconPapers View complete reference list from CitEc
Citations:
Downloads: (external link)
https://doi.org/10.26509/frbc-wp-202414 Persistent Link (text/html)
https://www.clevelandfed.org/-/media/project/cleve ... pers/2024/wp2414.pdf Full Text (application/pdf)
Related works:
Working Paper: On Commercial Construction Activity's Long and Variable Lags (2024) 
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:fip:fedcwq:98508
Ordering information: This working paper can be ordered from
DOI: 10.26509/frbc-wp-202414
Access Statistics for this paper
More papers in Working Papers from Federal Reserve Bank of Cleveland Contact information at EDIRC.
Bibliographic data for series maintained by 4D Library ().