An approach using SAT solvers for the RCPSP with logical constraints
Mario Vanhoucke and
José Coelho
European Journal of Operational Research, 2016, vol. 249, issue 2, 577-591
Abstract:
This paper presents a new solution approach to solve the resource-constrained project scheduling problem in the presence of three types of logical constraints. Apart from the traditional AND constraints with minimal time-lags, these precedences are extended to OR constraints and bidirectional (BI) relations. These logical constraints extend the set of relations between pairs of activities and make the RCPSP definition somewhat different from the traditional RCPSP research topics in literature. It is known that the RCPSP with AND constraints, and hence its extension to OR and BI constraints, is NP-hard.
Keywords: Project scheduling; RCPSP; AND/OR/BI constraints; SAT (search for similar items in EconPapers)
Date: 2016
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (8)
Downloads: (external link)
http://www.sciencedirect.com/science/article/pii/S0377221715008000
Full text for ScienceDirect subscribers only
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:eee:ejores:v:249:y:2016:i:2:p:577-591
DOI: 10.1016/j.ejor.2015.08.044
Access Statistics for this article
European Journal of Operational Research is currently edited by Roman Slowinski, Jesus Artalejo, Jean-Charles. Billaut, Robert Dyson and Lorenzo Peccati
More articles in European Journal of Operational Research from Elsevier
Bibliographic data for series maintained by Catherine Liu ().