Project schedule performance under general mode implementation disruptions
Jeroen Burgelman and
Mario Vanhoucke
European Journal of Operational Research, 2020, vol. 280, issue 1, 295-311
Abstract:
This paper presents a simulation study for a resource-constrained project scheduling problem with multiple alternatives. We decide on a set of baseline schedules at the project planning phase, resulting in options to switch between execution modes of activities during project execution. We assess the performance of the set of baseline schedules under general mode implementation disruptions. A simple, yet effective algorithm is presented to construct the set of baseline schedules. Moreover, a general disruption system is proposed to model different disruption types, disruption dependencies and disruption sizes.
Keywords: Project management; Execution alternatives; Matheuristic; Disruption system (search for similar items in EconPapers)
Date: 2020
References: Add references at CitEc
Citations: View citations in EconPapers (1)
Downloads: (external link)
http://www.sciencedirect.com/science/article/pii/S0377221719305430
Full text for ScienceDirect subscribers only
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:eee:ejores:v:280:y:2020:i:1:p:295-311
DOI: 10.1016/j.ejor.2019.06.050
Access Statistics for this article
European Journal of Operational Research is currently edited by Roman Slowinski, Jesus Artalejo, Jean-Charles. Billaut, Robert Dyson and Lorenzo Peccati
More articles in European Journal of Operational Research from Elsevier
Bibliographic data for series maintained by Catherine Liu ().