Quantitative Cost and Schedule Risk Analysis of Nuclear Waste Storage
Alexander Budzier,
Bent Flyvbjerg,
Andi Garavaglia and
Andreas Leed
Papers from arXiv.org
Abstract:
This study provides an independent, outside-in estimate of the cost and schedule risks of nuclear waste storage projects. Based on a reference class of 216 past, comparable projects, risk of cost overrun was found to be 202% or less, with 80% certainty, i.e., 20% risk of an overrun above 202%. Based on a reference class of 200 past, comparable projects, risk of schedule overrun was found to be 104% or less, with 80% certainty, i.e., 20% risk of overrun above 104%. Cost risk and schedule risk are both substantial for nuclear waste storage projects.
Date: 2019-01
References: View references in EconPapers View complete reference list from CitEc
Citations: View citations in EconPapers (1)
Downloads: (external link)
http://arxiv.org/pdf/1901.11123 Latest version (application/pdf)
Related works:
This item may be available elsewhere in EconPapers: Search for items with the same title.
Export reference: BibTeX
RIS (EndNote, ProCite, RefMan)
HTML/Text
Persistent link: https://EconPapers.repec.org/RePEc:arx:papers:1901.11123
Access Statistics for this paper
More papers in Papers from arXiv.org
Bibliographic data for series maintained by arXiv administrators (help@arxiv.org).